Randy Hudson (216142) | asked Mar 28 '07, 5:55 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
I had a project in a component in a stream.
I baselined the component, then removed the project from the component, and
delivered my workspace's changes to the stream.

Now, I want to re-load that project. In CVS, I could recreate a shared
empty project/module, then select replace with, another branch or version,
and select the version I want and reload it.

How do I resurrect something in Jazz?

Accepted answer


permanent link
John Camelon (1.7k14) | answered Mar 29 '07, 9:13 a.m.
JAZZ DEVELOPER
Open up the workspace editor. (The Open menu on selecting a workspace in
Pending Changes or Team Artifacts views).

You can add or replace components using other workspaces/streams,
baselines or snapshots there.

Hope that helps,
JohnC

Randy Hudson wrote:
I had a project in a component in a stream.
I baselined the component, then removed the project from the component, and
delivered my workspace's changes to the stream.

Now, I want to re-load that project. In CVS, I could recreate a shared
empty project/module, then select replace with, another branch or version,
and select the version I want and reload it.

How do I resurrect something in Jazz?

Ralph Schoon selected this answer as the correct answer

2 other answers



permanent link
Randy Hudson (216142) | answered Mar 29 '07, 10:56 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
"John Camelon" <jcamelon@ca.ibm.com> wrote in message
news:eugdei$3aj$1@localhost.localdomain...
Open up the workspace editor. (The Open menu on selecting a workspace in
Pending Changes or Team Artifacts views).

You can add or replace components using other workspaces/streams,
baselines or snapshots there.

This didn't help. The component contains 5 other projects, which have
continued to evolve since the baseline containing the 6th project before
deletion. I want to re-load only the 6th project.

permanent link
John Camelon (1.7k14) | answered Mar 29 '07, 11:11 a.m.
JAZZ DEVELOPER
Randy Hudson wrote:
"John Camelon" <jcamelon@ca.ibm.com> wrote in message
news:eugdei$3aj$1@localhost.localdomain...
Open up the workspace editor. (The Open menu on selecting a workspace in
Pending Changes or Team Artifacts views).

You can add or replace components using other workspaces/streams,
baselines or snapshots there.

This didn't help. The component contains 5 other projects, which have
continued to evolve since the baseline containing the 6th project before
deletion. I want to re-load only the 6th project.



You may need to reload the whole component and then accept whatever
additional change sets/baselines to bring you up to date. I am not
sure if there is a more optimal way of performing this in the UI at this
time.