RQM with Doors Classic - Reconcile
One answer
Monika,
It should work. I would check DWA and RQM integration in such case.
DWA check:
- Are you able to create link to DOORS requirement from RQM?
- Are you getting rich-hover for DOORS requirement from RQM?
- Do you have ensured DCN commands have run properly on while configuring DWA?
- Change in DOORS requirement is reflating on DWA?
- If yes then I would say DWA is configured properly.
Could you please share the version of DOORS and RQM you are using?
Regards,
Mehul
Comments
Hi Mehul,
- I can create links from RQM to Doors
- rich-hover in RQM is possible
- how can I check if DCN commands have run properly?
- change in req. is reflecting in in DWA
Version of RQM: 6.0.5 iFix007
Version of Doors: 9.6.1.10
Regards and thanks
Monika
Monika,
It appears like you have configured this integration correctly and reconciliation across given major versions is supported. I would suggest to contact support and log a ticket for further investigation.
Regards,
Mehul