Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Progress Bar in Scrum (Plan and Resource)

 Dear,


There is some way to set a start date for a task in Scrum templat of RTC? My question is because if I have a task assigned to a Resource in a Sprint that lasts 5 days and the task have a work estimate of 5 hours, but the resource is not working on it (And the resource doesn´t have any other task assigned) and have passed 2 days, the progress bar of this resource (and the progress bar of the sprint backlog) indicates that the resource is late on him work. But however there is enough time for the resource to finish the task.

So there is some way to avoid that the progress bar of the resource (and the sprint backlog) doesn´t show that the resource is late on his work, when there is still time to finish the task? I mean its possible set a start date to the task and in that way have a precision about in what date is really late the resource? Becuase what I understaind is that the RTC calculates arbitrarily and proportionally the daily progress
that the resource must achieve.

This information is important for me because is shown in my boss's reports.

Thanks in advance.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Apr 09 '18, 2:58 p.m.

Question was seen: 1,154 times

Last updated: Apr 09 '18, 2:58 p.m.

Confirmation Cancel Confirm