Issue : Owner of the workitem changes when creating a child workitem to it in the Plan view.

Hello Team,

We have a Story workitem listed in the Plan View.
Story is in new state and Owned by "A"
In the plan view, try to create a child task, assign it to owner "B".
Move the task to "In Progress".
Story's Owner is now changed to "B".

How can this happen ? Is this the actual behaviour of the workitems in the plan view.
However same doesnt happen, when the workitems are created in the normal view.

Please suggest if this is an issue.

Thanks.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Jan 29 '18, 3:01 a.m.

Question was seen: 1,116 times

Last updated: Jan 29 '18, 3:01 a.m.

Confirmation Cancel Confirm