Can I limit estimation filed to only days?
Hi,
I've added 'Estimation' files into my RTC work items (for Features only). I can insert days, min, hours, weeks... when I insert '10 days' the files is auto correct to hours and show 80 hours. how can I set it to show the estimation filed according to the I insert and not auto correct my selection?
Thanks,
Bareket
|
One answer
Ralph Schoon (63.6k●3●36●46)
| answered Jan 04 '18, 5:45 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER I don't think so. There is a property in Eclipse->Project Administration->Project Configuration->Configuration Data->Planning->General->Estimate Attributes->Display estimates in hours
|