How do I show requirements changes in RDNG/RTC without baseline
procedure to show requirements changes in RDNG/RTC without baseline.
I should be able to track the requirement changes based on due date also and email notification to the users based on the due date expiry.
There may one or more requirement change in any requirement specification which are discussed in the meeting by specific due date. I just want show only the requirement changes which were discussed in the meeting and which needs to fixed by due date.
One answer
Hi,
you can view the artifact changes for requirements as documented in https://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.4/com.ibm.rational.rrm.help.doc/topics/t_view_artifact_revs.html
By the way, you can enable local configuration management for DNG without enabling or using Global Configuration management. GC is needed if you want to link local config management enabled DNG modules / requirements to versioned test plans / test cases.
- Arne
Comments
Could you please let me know the procedure to enable local configuration management for DNG without GC.
Is that doable in 6.0.2 I thought GC was all or nothing .. and how does one enable it purely for DNG - is that running jts/server setup ?
Thx
Hi Ulf Arne Bister,
Is it possible to generate the report, on the requirement changes instead of viewing the changes using history option in DNG both at module and project area level?
That is at least material for two new excellent questions on jazz.net :-)
Local config: https://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.5/com.ibm.jazz.vvc.doc/topics/t_admin_stub-cfgSection.html
Notice how Geoff pointed out that once you use more than just DNG the real benefit is using it in the context of global configuration management.
As for reports, if you look at Reports in DNG and at the RPE templates there is one called Audit History. Is that what you need?
Comments
Vani B
Sep 22 '17, 1:26 a.m.CLM RM version is 6.0.4 and global configuration is not configured