Jazz Register Log in
Jazz Forum Welcome to the Jazz Community Forum

Welcome to the Jazz Community Forum

Connect and collaborate with IBM Engineering experts and users

can get estimated hours from Children?

i have one parent task and 4 child task. i will give estimation to children task but we did not give estimation for parent task. now my question is, can i get estimation hours from Children?

0 votes



One answer

Permanent link

Estimates roll up. So if your parent has a progress editor presentation, you should be able to see the total of all the estimates on the children by viewing the parent. If you don't have the progress bar in your work item presentation, you can see this in a plan view.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,048

Question asked: Jul 26 '17, 7:29 a.m.

Question was seen: 1,683 times

Last updated: Jul 28 '17, 9:08 a.m.

Confirmation Cancel Confirm