Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Does full ODS job mean full Data Mart job?

 We inadvertently ran a full load ODS DCC ETL job this weekend. Once that job completes, would it be advisable to run a full load job on the Data Mart? 


Thanks,
Ryan

0 votes



One answer

Permanent link

Hello Ryan,

most of the jobs in the data mart section collect metrics for the current day, so they are not affected by the delta / full setting.
Other jobs in the section, like timesheets are affected like those in the ODS.

As a general rule, unless you have specific issues you want to fix, a full load is not required; even in this case where you run already the full load for the ODS part.

Best Regards
Francesco Chiossi

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,495

Question asked: Jul 16 '17, 2:42 p.m.

Question was seen: 2,694 times

Last updated: Jul 18 '17, 4:19 a.m.

Confirmation Cancel Confirm