 I just ran an unscheduled full load ODS Data Collection job. A delta load job is scheduled for midnight tonight, but we are sure it won't be finished by then. Will this be a problem? Or will the delta load jobs just not run until the full load has completed? I've disabled the data mart jobs for tonight.


Would really appreciate a fast response here! Thanks!

0 votes

Comments

 That is, the full load job will not finish before the delta load job is scheduled to start. Will that delta job not execute until the full job has finished?



3 answers

Permanent link

Sorry, just saw this, but the delta won't run until the full load completes.  But you've probably already figured that out by now!

0 votes

Comments

  Thank you Jackie! I see that everything is running smoothly.


Permanent link

 Thank you Jackie! I see that everything is running smoothly.

0 votes


Permanent link

 As a follow up question, once the ODS full jobs run, should we also run a full Data Mart job? Or can we just continue running delta loads?

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,485

Question asked: Jul 13 '17, 7:36 p.m.

Question was seen: 3,157 times

Last updated: Jul 16 '17, 2:40 p.m.

Confirmation Cancel Confirm