It's all about the answers!

Ask a question

Package grouping in Pending Changes View


Goran Pop-Jordanov (131) | asked Jul 13 '17, 11:41 a.m.

When comparing streams in Pending Changes View in RTC, the differences are grouped by the corresponding changesets.
In some cases, it is preferable to group the changes by project/folder/package.
Is there a was to do so?

Thanks.

Accepted answer


permanent link
Ulf Arne Bister (1.3k413) | answered Jul 20 '17, 11:58 a.m.

Goran,
if I remember correctly in the Eclipse client you can mark all change sets in Change Explorer (opened when you compare streams) by i.e. mouse left-click, hold Shift, left-click lowest and then Open in Change Summary from right-click context menu. Make sure to have just change sets in your selection.

Is this what you were looking for? Then please mark this answer as accepted.

- Arne

Goran Pop-Jordanov selected this answer as the correct answer

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.