Why is Sprint Backlog not in Current Plans view?
Hi,
I use the Plans section a lot. There is the Current Plans and All Plans.
Something to note: I have 2 teams in the same Project Area:
Team 1- ITSS Team
Team 2- IIQ Team
When I access the Current Plans section, I only see the current Sprint Backlog for team 1 and 2 + Spring Backlog for team 1. However I don't see the Sprint Backlog for team 2. I am not sure why.
When I access the All Plans view, I do see all plans correctly.
What change I need to do to see the Sprint Backlog of team 2 in the Current Plans view?
Thank you
|
3 answers
Have you chosen to display All Team Areas in the Current Plans section?
Comments
Maxime Girard
commented May 10 '17, 8:35 a.m.
Hi,
I have added a comment above. I think it is because this backlog is under a timeline that is not checked as the "project timeline".
Geoffrey Clemm
commented May 11 '17, 12:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Whether or not the timeline is checked as the "project timeline" should have no effect on whether any of the plans for iterations in that timeline appear in the Current Plan view.
|
Geoffrey Clemm (30.1k●3●30●35)
| answered May 11 '17, 1:00 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER The "current plans" view should show all plans for:
Comments
Maxime Girard
commented May 15 '17, 1:23 p.m.
- all iterations that are selected as the backlog iteration for a timeline. How exactly I do that? I don't see where is the option to set an Iteration as the Backlog Iteration for a timeline.
Thank you
Geoffrey Clemm
commented May 20 '17, 12:53 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
To set the backlog iteration, in the WebUI, edit the project area ("Manage this project area"), and select the Planning->General tab.
Maxime Girard
commented May 23 '17, 3:20 p.m.
I have the "Manage this project area" but I don't see any sections named "Planning" with a General Tab.
I would like so much to post screenshots of what I see... but I can't. It seems like I need 60 points or something like that on this site before I can do so.
If you could post a screenshot of this settings, it would help a lot. Thanks.
Maxime Girard
commented May 23 '17, 3:36 p.m.
Ok,
I was able to change the option. I used the Eclipse RTC client, opened my project area, went to the tab Process Configuration -> Configuration Data -> Planning -> General. I selected the Backlog and click on a button on the top right that said: Mark the selected Iteration as Backlog Iteration" and clicked save.
It worked ok. I think I may not have the latest Web RTC client and I didn't have this option.
|
I will post here for the answer.
I was able to change the option. I used the Eclipse RTC client, opened my project area, went to the tab Process Configuration -> Configuration Data -> Planning -> General. I selected the Backlog and click on a button on the top right that said: Mark the selected Iteration as Backlog Iteration" and clicked save.
It worked ok. I think I may not have the latest Web RTC client and I didn't have this option.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Can I add more details to better explain my problem?
What iteration is the backlog set to, does it have a start and an end, is it set to current?
Hmmm,
Also, there is no Start and End date set on this Backlog.
Whether or not an iteration has a start/end date should have no effect on whether plans for that iteration appear in the Current Plans view. Also, whether or not an iteration is in the project timeline should have no effect on whether plans for that iteration appear in the Current Plans view.