IBM RTC Sprint Burndown shows no data available

 Hello,


We are using RTC 6.0.1 Scrum Template. We have configured Plan for one of the sprint but burndown shows no data available where there are 100s of items planned for Sprint.

What can be the cause for the same?

Thanks.

0 votes


Accepted answer

Permanent link

 If you can't  see data like this, it usually has the following reasons:


  • The data warehouse is not set up, running, or the data collection has not happened
  • The data is missing some criteria and therefore does not show up in the widget 
In almost all cases I have seen one of the reasons from above caused these issues. Try creating a report in the Report Builder that selects work items filed against Team 1 and planned for Sprint 4. Does that show data? Check if you have stories with story points, because burn down/up data uses that data.

Check with your administrator that data collection is working and if it does ask them for if you could have missed something in your configuration. 

And repeating that there are many work items is not going to fix the problem. Something, either data collection, or the widget configuration, or the data you produce (category (Filed against)/target (planned for)) work item types and relationships is wrong, causing no data to be seen in the report. 

IBM Rational Product User selected this answer as the correct answer

0 votes


One other answer

Permanent link

Hi, (I'm not an IBM Expert)

Are you talking about a "plan" or a "report" - Burndown?

If you are talking about the Report - To use from the OOTB scrum reports it will use the Data Warehouse or DCC component.

If the Data is all correct and you have setup the Team, Category and timeline with "Tasks" with Estimates and the Data warehouse has ran then you should see information however you may wish to check all of these things.

 Regards

Matt Muller

0 votes

Comments

 Hello Matt,


Thank you so much for your reply. We are facing problem in Plan and Report on dashboard both. We have created a plan which is owned by Team 1 and Iteration = Sprint 4. Plan has 100s of items with estimations and Owned by as users withing Team 1. But In plan view, burndown shows no data available. Also, report on dashboard for current sprint burndown also shows no data available.


Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Mar 24 '17, 10:18 a.m.

Question was seen: 2,457 times

Last updated: Mar 28 '17, 7:33 a.m.

Confirmation Cancel Confirm