Excluding work types from a task board view


Sean Burke (3789126208) | asked Mar 23 '17, 12:27 p.m.

 I have task board view of a plan (RTC 6.02)  I want to exclude certain work item types  off of the task board.  For example I don't want to see milestones and tasks on the task board.  I would image this is done through the exclude box.  What would be the syntax to include certain work item types 

One answer



permanent link
Lily Wang (4.9k714) | answered Mar 24 '17, 4:58 a.m.

You can use Exclude Expression with "type:Task". If you'd like to include certain type, you may use "!type:Task".