Executing a Test Case & Associate Results with a Test Pl

I have a Test Case contained within a Plan; when I go to execute it, navigated to via the plan, I expected the "Associate Results with a Test Plan" to be checked on automatically, but it isnt. Why is this?

Now my real problem: when I check the "Associate Results with a Test Plan" ... no Plans appear in the list for selection, despite there being 3 Plans already defined in RQM. Why is this?

Thx!

0 votes



2 answers

Permanent link
I have a Test Case contained within a Plan; when I go to execute it, navigated to via the plan, I expected the "Associate Results with a Test Plan" to be checked on automatically, but it isnt. Why is this?

Now my real problem: when I check the "Associate Results with a Test Plan" ... no Plans appear in the list for selection, despite there being 3 Plans already defined in RQM. Why is this?

Thx!


John

Can you confirm which version you're using .. I just tried what I believed was what you're doing - agreed, the "associate with Test Plan" is not automatically toggled off despite you issuing the run command from the test case directly within the test plan - I believe this may be due to the fact that a test case can belong to multiple plans - don't see it as a bug, but may be worth asking the question of the development team. why it doesn't default to the plan in question if you've selected to run from that plan level.

As for the plan type not being available on the drop down after you toggle that on .. I believe that was a bug in 1.0x version .. can you confirm your version number

0 votes


Permanent link
Yes using V2.0.

as discussed: the plans are only displayed in the drop down if the Test Execution Record is set to "New" or has an existing properly defined Test Execution Record associated with it.

I have a Test Case contained within a Plan; when I go to execute it, navigated to via the plan, I expected the "Associate Results with a Test Plan" to be checked on automatically, but it isnt. Why is this?

Now my real problem: when I check the "Associate Results with a Test Plan" ... no Plans appear in the list for selection, despite there being 3 Plans already defined in RQM. Why is this?

Thx!


John

Can you confirm which version you're using .. I just tried what I believed was what you're doing - agreed, the "associate with Test Plan" is not automatically toggled off despite you issuing the run command from the test case directly within the test plan - I believe this may be due to the fact that a test case can belong to multiple plans - don't see it as a bug, but may be worth asking the question of the development team. why it doesn't default to the plan in question if you've selected to run from that plan level.

As for the plan type not being available on the drop down after you toggle that on .. I believe that was a bug in 1.0x version .. can you confirm your version number

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 08 '09, 3:32 a.m.

Question was seen: 3,750 times

Last updated: Sep 08 '09, 3:32 a.m.

Confirmation Cancel Confirm