We're trying to figure out the best way to use RTC for a team that do not work in the agile way. In particular there are no natural iterations to "base" the work on.

One of the issues we've stumbled upon is sorting the work items based on their Due Date, e.g. in a team iteration plan (in the simple team process). You may sort the list on various critera: Priority, Planned Time etc but not on Due Date.

It is possible to get the Due Date shown by including it in the View Layout settings but we really would like to have it sorted in the Due Date order.

Is this impossible or are we missing something obvious?

Regards/Roger

1

0 votes



2 answers

Permanent link
On Tue, 08 Sep 2009 08:22:50 +0200, rogerpersson
<roger> wrote:

We're trying to figure out the best way to use RTC for a team that do
not work in the agile way. In particular there are no natural
iterations to "base" the work on.

One of the issues we've stumbled upon is sorting the work items based
on their Due Date, e.g. in a team iteration plan (in the simple team
process). You may sort the list on various critera: Priority, Planned
Time etc but not on Due Date.

It is possible to get the Due Date shown by including it in the View
Layout settings but we really would like to have it sorted in the Due
Date order.

Is this impossible or are we missing something obvious?

Regards/Roger


this is currently not possible, as it is prevented by the following two
bugs:

93936: Dates are not rendered correctly
93935: NPE when sorting by due date

--
MikeS
Jazz Agile Planning team

0 votes


Permanent link
On Tue, 08 Sep 2009 08:22:50 +0200, rogerpersson
<roger> wrote:

We're trying to figure out the best way to use RTC for a team that do
not work in the agile way. In particular there are no natural
iterations to "base" the work on.

One of the issues we've stumbled upon is sorting the work items based
on their Due Date, e.g. in a team iteration plan (in the simple team
process). You may sort the list on various critera: Priority, Planned
Time etc but not on Due Date.

It is possible to get the Due Date shown by including it in the View
Layout settings but we really would like to have it sorted in the Due
Date order.

Is this impossible or are we missing something obvious?

Regards/Roger


just for the reference, it is possible to create a new sort mode:
http://www.poshnet.ch/jing/2009-09-08_1757.png

however, when trying to sort by attribute values which are not set on some
work items, the sorter fails in the Eclipse UI :(

--
MikeS
Jazz Agile Planning team

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 08 '09, 2:08 a.m.

Question was seen: 5,071 times

Last updated: Sep 08 '09, 2:08 a.m.

Confirmation Cancel Confirm