Hi
Sometimes when I view a Burndown chart, it will show data that I don't understand. One time the last point on the chart was actually showing as two points, when you hover over the points, it actually showed two different values so I was not sure which one is correct. I assume this data is collected from the Data Warehouse? Could it just be a fluke in how it was charted? Any insight to what is happening here would be greatly appreciated.

Thanks!

0 votes



2 answers

Permanent link
Hi
Sometimes when I view a Burndown chart, it will show data that I don't understand. One time the last point on the chart was actually showing as two points, when you hover over the points, it actually showed two different values so I was not sure which one is correct. I assume this data is collected from the Data Warehouse? Could it just be a fluke in how it was charted? Any insight to what is happening here would be greatly appreciated.

Thanks!


I believe I just learned that one of the data points is "live" and the other is from the Data Warehouse. That would explain it! If there is anything else that you could tell me, that would be great. Thanks!

0 votes


Permanent link
Yes. The last point is a live point that shows the current value. The other points come from the data warehouse and correspond to midnight of each day.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 03 '09, 4:20 p.m.

Question was seen: 4,419 times

Last updated: Sep 03 '09, 4:20 p.m.

Confirmation Cancel Confirm