Creating a User Story and Task in one step
John Steele (27●1●14)
| asked Jan 17 '17, 1:34 p.m.
retagged Jan 20 '17, 4:59 p.m. by Ken Tessier (841●1●7) Since a User Story (a Plan Item) and at least one Task (an Execution Item) are required to create a story, is it possible to script the story creation process to include the creation of one Task item? |
Accepted answer
You can create templates that include multiple work items and relationships. https://jazz.net/help-dev/clm/index.jsp?topic=%2Fcom.ibm.team.workitem.doc%2Ftopics%2Fc_using_templates.html
-michael
John Steele selected this answer as the correct answer
|
Your answer