Setting hours per day in CCM
How do I change the default hours per day set in IBM CCM? I can see that I can update the hours for individual team members but I couldn't find an option to change the value at a project level. Please help.
|
One answer
Hi Santhosh,
This can be changed on the project, but opening up the process configuration. (Right-click on project > open).
Select the process configuration tab.
From here expand the following project configuration > configuration data >planning and select work environment. On the page you change the work hours and days for a given project.
Hope this helps.
Many Thanks James
|