Setting hours per day in CCM

One answer

Hi Santhosh,
This can be changed on the project, but opening up the process configuration. (Right-click on project > open).
Select the process configuration tab.
From here expand the following project configuration > configuration data >planning and select work environment. On the page you change the work hours and days for a given project.
Hope this helps.
Many Thanks James