Is there a way to create a work item template that does the following scenario:

Story - Do Something
--Linked Task with title "Develop -"
--Linked Task with title "Create a Test for -"
--Linked Task with title "Create a Requirement for -"

So...3 work items created for some story and links them to the story. 

One answer



permanent link
Eric Jodet (6.3k5109120) | answered Nov 05 '13, 2:08 a.m.
JAZZ DEVELOPER
 Hello,
this is possible OOTB:
1 - create your work items, links (like tasks child of the parent story)
2 - create a query that will pick-up all of these
3 - right click the work items in the Work Items view and select "Create work item template"
4 - give the template a name
5 - press "finish"
done
You can no use this template.