Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

How to resolve issue of planned start date not populating as desired?

For any workitem I add in the plan with iteration and time line "[10/3/16-10/7-16]",  the workitem takes the plan start date as the creation date of the workitem even after creating snapshot of type "Planned".

The Constraint type is "Start No Earlier than" and Constraint Date is "10/4/16", 

The conflict is indicated by an error icon in the workitem column. on mouse hover the error shown is as "The work item has a Start No Earlier Than constraint for 10/4/16, but it is planned to start on 7/14/16.".

How to resolve this issue so that the workitem gets planned start date as 10/4/16?

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 14 '16, 7:24 a.m.

Question was seen: 3,584 times

Last updated: Jul 14 '16, 7:35 a.m.

Confirmation Cancel Confirm