How is the 'accumulated time' calculated in the Formal template?


Kumar Singal (111) | asked Jun 12 '15, 9:25 a.m.
retagged Jun 19 '15, 4:27 p.m. by Ken Tessier (84117)
We're using the Formal Template in RTC. In the 'Work breakdown and Schedule' Plan view, one of the columns references the 'Accumulated time' which is a read-only field whose value is calculated behind-the-scenes.

We haven't quite been able to figure out how that field is calculated to be able to manipulate it on the gantt chart. Does anyone have any insight or can explain it better than any of the articles on jazz.net?

Thanks!

Comments
Ralph Schoon commented Jun 15 '15, 2:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Please see

https://jazz.net/library/article/657
https://jazz.net/library/article/663

for more information about the traditional scheduler. I am not sure if it answers your question, but I unfortunately don't have a traditional planning project with useful data to check.


Ralph Schoon commented Jun 15 '15, 2:56 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Please note, the data computed by the plan is not an attribute of the work item. It is a value that is dynamically computed and presented on the plan.

2 answers



permanent link
Sumant Renukarya (1.1k23339) | answered Jun 15 '15, 3:15 p.m.
 Hello Kumar

Adding to Ralph, perhaps the below thread might help?

https://jazz.net/forum/questions/148839/accumulated-time-in-roadmap-view-of-a-plan

permanent link
Ken Tessier (84117) | answered Jun 19 '15, 4:27 p.m.