Current Iteration does not move to next iteration as time pass on

I have Current Iteration setup, and hope Current Iteration automatically move to the next iteration when End Date is passed.   But it is not happening.

Any ideas?




0 votes

Comments

Bin,

The Version I have worked with V4.0.7 you have to manual move the "Current Iteration".


Accepted answer

Permanent link
You are supposed to set the current active iteration e.g. as scrum master. It is a process decision to do so and not automated.
Bin Yang selected this answer as the correct answer

0 votes

Comments

Ralph:

Good to know this is the manual process to move Current Iteration forward..

I do think it is a useful feature to have current iteration move automatically, if there are start/end dates configured for iteration.

Thanks.   

there is always sprint close out work that needs to be done.. there is no way to do this automatically.  so, when you close the sprint, you advance to the next as you are right there

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,122

Question asked: Jun 13 '16, 9:53 p.m.

Question was seen: 1,373 times

Last updated: Jun 14 '16, 8:36 a.m.

Confirmation Cancel Confirm