Current Iteration does not move to next iteration as time pass on
Accepted answer
You are supposed to set the current active iteration e.g. as scrum master. It is a process decision to do so and not automated.
Comments
Ralph:
Good to know this is the manual process to move Current Iteration forward..
I do think it is a useful feature to have current iteration move automatically, if there are start/end dates configured for iteration.
Thanks.
there is always sprint close out work that needs to be done.. there is no way to do this automatically. so, when you close the sprint, you advance to the next as you are right there
Comments
Matt Muller
Jun 14 '16, 7:26 a.m.Bin,
The Version I have worked with V4.0.7 you have to manual move the "Current Iteration".