Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

can we create a baseline for work item in RTC

 can we create a baseline for work item in RTC

0 votes


Accepted answer

Permanent link
If you expect an informed answer, please consider to provide more information. See  How should I ask a question in the Forum if I want to receive useful answers? for some considerations for asking questions.

In RTC a "Baseline" is a special, re-creatable configuration of changes in an SCM component. There is no baseline concept for work items that I am aware of.
Neeraj Malik selected this answer as the correct answer

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023

Question asked: Mar 16 '16, 3:55 a.m.

Question was seen: 1,406 times

Last updated: Mar 16 '16, 4:17 a.m.

Confirmation Cancel Confirm