can we create a baseline for work item in RTC


Neeraj Malik (23121) | asked Mar 16 '16, 3:55 a.m.
 can we create a baseline for work item in RTC

Accepted answer


permanent link
Ralph Schoon (63.3k33646) | answered Mar 16 '16, 4:17 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
If you expect an informed answer, please consider to provide more information. See  How should I ask a question in the Forum if I want to receive useful answers? for some considerations for asking questions.

In RTC a "Baseline" is a special, re-creatable configuration of changes in an SCM component. There is no baseline concept for work items that I am aware of.
Neeraj Malik selected this answer as the correct answer