Kanban view: How can I view the specific Work in Progress Limits for each Owner and Column?


Thomas Schönheim (134) | asked Jan 28 '16, 8:32 a.m.
edited Jan 28 '16, 9:03 a.m.
Hi,
after creating a Kanban view and group by owner, I add the Work in Progress Limits to the column.

... every Owner gets the column summary count of the Work in Progress Limits.
I would expected, that the count progress is specific for every Owner.

How can I view the specific Work in Progress Limits for each Owner and Column?

Best regards,
Thomas.

Accepted answer


permanent link
Ralph Schoon (63.1k33646) | answered Jan 28 '16, 9:21 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
As far as I am aware the limits are for the whole plan and not for an individual. If you group by owner you can see the columns and relatively easy see the work items for each owner in the columns, but there is no individual count for how many in each section shown.
Thomas Schönheim selected this answer as the correct answer

Comments
Thomas Schönheim commented Feb 01 '16, 4:50 a.m.

Hi Ralph,

thanks for your answer. I will rise an enhancement request.