Cumulative estimate per team member?

In the sprint planning meeting we estimate task durations together and plan the tasks for the according iteration.

If one team member gets multiple tasks in same iteration one can easily lose the overview of "well balanced" workload over all members.

Tried to solve it using available widgets / queries but did not succeed.


Is there a way to create something like: "Cumulative estimated time per team member and iteration"?

0 votes



One answer

Permanent link
 Have you checked out the Planning feature in RTC,
It comes by default below is one view that is there by default and the one you are looking for:
You can use https://jazz.net/library/article/593 for understand more on RTC Planning.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Oct 09 '13, 2:46 p.m.

Question was seen: 4,318 times

Last updated: Oct 09 '13, 11:51 p.m.

Confirmation Cancel Confirm