Need to make a field as a mandatory
Accepted answer
Hi Ankit
You can follow the below technote( How to set an Attribute mandatory in IBM Rational Team Concert Work Items):
http://www-01.ibm.com/support/docview.wss?uid=swg21445897
Also, sharing some useful information:
Modifying operation behavior (preconditions and follow-up actions) in project areas and team areas
http://www-01.ibm.com/support/knowledgecenter/SSYMRC_6.0.0/com.ibm.jazz.platform.doc/topics/t_mod_operation_behavior.html?lang=en
If this answers your question please mark it as accepted.
Regards,
Rohit
You can follow the below technote( How to set an Attribute mandatory in IBM Rational Team Concert Work Items):
http://www-01.ibm.com/support/docview.wss?uid=swg21445897
Also, sharing some useful information:
Modifying operation behavior (preconditions and follow-up actions) in project areas and team areas
http://www-01.ibm.com/support/knowledgecenter/SSYMRC_6.0.0/com.ibm.jazz.platform.doc/topics/t_mod_operation_behavior.html?lang=en
If this answers your question please mark it as accepted.
Regards,
Rohit
Comments
Hi Rohit,
Thanks for your answer,its helps me alot to make a mandatory field.
But now i am facing some issue related to the same. When i am making actual time spent as a mandatory field, i am getting error "Could not save work item. Time remaining is not valid". Please help me on this and suggest me how to proceed.
RTC supports two modes
- Time Spent
- Time remaining
If you use the time remaining mode, you have to make sure that the numbers add up. RTC takes the time in the Estimate field (or the corrected Estimate, if you provide one) and the time spent is Estimate-Remaining (in the time spent attribute). If that calculation fails e.g. goes negative, you see that error.
Thanks Ralph