Norman Dignard (356696177) | asked Jan 11 '16, 8:36 a.m.

One project manager wants a simple status report on work items but I haven't been able to figure it out.

Basically he wants a simple table listing summary counts for each work item type (epics and stories), showing the number of records completed, in progress, not started based on their priority (high, medium, low).

I've been able to generate 2 separate reports using JRS showing counts by status or counts by priority but not one combining both. We have jrs installed but I have not have much luck with it

One answer



permanent link
Arne Bister (2.6k12832) | answered Jan 13 '16, 4:54 a.m.
JAZZ DEVELOPER
Norman,

will the info in https://jazz.net/library/article/1470 help you achieve the result?

Please mark this answer as accepted if it does.

gg,
Arne

Comments
Norman Dignard commented Jan 18 '16, 12:09 p.m.

Your answer, while addressing part of my issue (editing the sql) to get the data, does not go into how to get that back into JAZZ as a pivot table type of report.