How do you add additional test cases to a paused TSER

I created a TSER containing multiple test cases, executed some of the test cases and paused the TSER. Additional requirements resulted in the need to add more test cases to the TSER. How can this be done?

0 votes



One answer

Permanent link
 Len,

Testcase can not be added to running/paused TSER, you need to add it to Testsuite and create new TSER.

Regards,
Mehul

0 votes

Comments

Mehul - Thanks for the answer

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Oct 16 '15, 3:26 p.m.

Question was seen: 1,734 times

Last updated: Oct 19 '15, 8:17 a.m.

Confirmation Cancel Confirm