It's all about the answers!

Ask a question

Why does CLM 6.0 setup hangs on LQE Finalize Application?


Timothy McKemy (1082317) | asked Jul 28 '15, 1:34 p.m.
I am trying to complete the setup of CLM 6.0 but it hangs at the LQE Finalize Application step. Any idea why? The environment is Windows 2012 R2, 6 GB RAM, SQL Server, Tomcat. All CLM pieces are being installed except RELM. The same thing happens even if RELM is included in the installation.

One answer



permanent link
Timothy McKemy (1082317) | answered Jul 28 '15, 1:49 p.m.
The reason it hung was that a popup blocker was preventing a web page the finalization opens from opening.