It's all about the answers!

Ask a question

Filed against default seems to change on its own


Jim Bomhdia (9256) | asked Jun 15 '15, 1:38 p.m.
I have noticed that the value that is filled into Filed against changes depending on what user creates the Task. If I create the Task Filed against is set to BAU. Another user gets a result of "Escalated" when using the exact same steps to produce the Task. And on the same project in the same plan. A third user gets a result of BAU like me.

I'd prefer not to set an explicit default. I just would like to know how that default is created and why it is different per user.

One answer



permanent link
Kevin Ramer (4.5k9186201) | answered Jun 15 '15, 1:43 p.m.
Filed Against are Work Item Categories which in turn map the Project Area or some Team Area.   I'd guess that RTC is making the suggestion of Filed Against based on the membership of the logged in user.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.