How can I get the DONE workitems in a Plan Kanban view?

I am not excluding any workitem, and I have several workitems in DONE status, but they are NOT displayed on a Plan View if I select Kanban. However, they are displayed if I select Flat or Tree.

Is that a limitation? why is that? I need to see the DONE items on a Kanban view.

Thank you,

Isabel Torres

0 votes


Accepted answer

Permanent link
Isabel,
- Check your plan view exclusions
- Check your plan view Column Display
- You may also need to scroll to the right to see all the columns.

Shawn
Isabel Torres selected this answer as the correct answer

1 vote

Comments

Thank you Shawn, I have found out my mistake... the "Done" status was not associated to the "Closed" group, in fact, it was not associated to any group.

Thank you so much!

Isa

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: May 26 '15, 12:26 a.m.

Question was seen: 2,319 times

Last updated: May 26 '15, 10:49 a.m.

Confirmation Cancel Confirm