report generation hours(effort) against weekly work
Hi,
i would like to genereate a report/graph which shows the effort( or hours in this case) needed to complete the tasks for each week.(showing hours on the y axis and weeks on the x axis). On the graph i would also like to be able to plot the tasks that we managed to conquer during that week and the tasks still pending... is this possible? thanks Rob |
4 answers
farrugiarobert wrote:
Hi, Hi Rob, Work items currently have an "estimate" field. Is this the data you would like to plot? (Note that estimate is obviously a different thing than the time *actually* required to complete the work). If it's not, how would you calculate the duration? My guess is that it would simply be the amount of time between when the work item entered an IN_PROGRESS state and the time it entered a CLOSED state. In the data warehouse, we currently don't collect information about the estimates, but that might be a good candidate for us to add. james |
Hi,
Yes, i noticed that estimates is not found in the data ware house. it would be a good idea to be added since one can use it to calculate the effort needed to be done in a fixed period of time. Keep me posted Thanks. |
Minor addition: APT will add another field to a work item to track the
time spent to do "the work" Dirk James Moody wrote: farrugiarobert wrote: |
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.