How to display time remaining in plan views?
We switched a project from using Time Spent to Time Remaining. It's working in work item views. But when configuring a plan view to add a Time Remaining column, the only option available is Time Spent.
I thought this was because of the single field to hold this Time Spent/Time Remaining information. But when I look at the actual data in the plan views, it really is displaying Time Spent. For example, a Task has an estimate of 12 hours. The value displayed as Time Remaining in the work item presentation is 4 hours. The column labeled "Time Spent" in the plan view for that Task displays 8 hours. How can we display Time Remaining in a plan view? The server is running 4.0.0.1. |
Accepted answer
Ralph Schoon (63.5k●3●36●46)
| answered Mar 08 '13, 3:11 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
As far as I know, unfortunately the presentation in the work item attribute presentation calculates time remaining and estimate to time spent and then displays the result. So, unfortunately I think you have to display time spent and estimate and then do the math. The related work item to add a real time remaining attribute has unfortunately not being addressed yet, as far as I know.
Mark Ingebretson selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.