How to get a report for sum of 'Time estimated' for all work items for each user in RTC?
One answer
I got it from RRDI.
Go to Query Studio.
From ODS -> Request Area -> Request, drag Project Name, Planned Work, Owner Name, External Key1.
Open the report in Report Studio, select Planned Work and click on Summation icon (Total)
I also Grouped on the basis of Project Area, so I got sum of 'Estimate' per project area for each user.
Comments
Abhinav Mishra
Apr 14 '15, 9:13 a.m.From RRDI ,i am not sure how to get it done.But by using BIRT we can achieve that.