How load is calculated at a plan
Hi,
I am trying to understand how load is calculated at plan:
Process template: Scrum
The setup is:
- A project area with scrum template
- 2 teams in this project area
- 1 iteration, sprint1 which covers only a single day.
- 1 user declared on both teams: he works at 50% for the first team and 0% for the second team.
Use case 1:
- plan with owner "project area" and iteration "sprint1" => the global load is 8 hours available
Use case 2:
- plan with owner "team1" and iteration "sprint1" => the gloabel load is 4 hours
- plan with owner "team2" and iteration "sprint1" => the gloabel load is 0 hours
We don't understand why the global load is 8 hours in the use case1 while the user work only 4h.
If you remove the user from the team2 where he works at 0%, the global load will be 4h.
Can you kindly explain?
-Thanks-Samar
|
One answer
Ralph Schoon (63.6k●3●36●46)
| answered Mar 20 '15, 10:32 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Please see in the library: Progress Bars, Load Bars, and the importance of estimating your work in Rational Team Concert.
Comments
Ralph Schoon
commented Mar 20 '15, 10:34 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You might also want to check with An Overview of Project Fundamentals in Rational Team Concert 3.0 to understand the fundamental data that is used.
|