Progress bar in iteration planning

As trivial as it seems to me, I have trouble finding out how the "Expected work Hours" and subsequently the "Hours behind" are calculated in the Iteration plans...


Any help?

Jan

0 votes



5 answers

Permanent link
JanVdP wrote:
As trivial as it seems to me, I have trouble finding out how the
"Expected work Hours" and subsequently the "Hours
behind" are calculated in the Iteration plans...


What we do to calculate the projection is pretty straightforward: We
take two ratios and compare them. The first ratio is the sum of work
that has been resolved against the sum of work that is still remaining.
The second ratio is the sum of real time that's over again the sum of
real time that's upcoming.

projection= work_time_DONE/work_time_REMAIN - real_time_DONE /
real_time_REMAIN

You are behind if this value is negative and vice versa.

The expected work hours is your total work times the real time progress,
e.g. when 20 of 40hrs are over, half of your work is expected to be done
(5 of 10pts).

The work hours behind/ahead is difference of expected work hours done
and actual work time done, e.g. 20 of 40hrs real time are over, but only
1 out of 10 story points have been achieved. As the real time ratio is
0.5 we expect 10*0.5=5 story points to be done. As only 1 point is done,
you are behind by 4 points.


--
Cheers, Johannes
Agile Planning Team

0 votes


Permanent link
Johannes thank you for this explanation, we are currently not using story points, they are set to 0 in our tasks. How does that affect expected work hours and ahead/behind number of hours?

Thank you
Lila

JanVdP wrote:
As trivial as it seems to me, I have trouble finding out how the
"Expected work Hours" and subsequently the "Hours
behind" are calculated in the Iteration plans...


What we do to calculate the projection is pretty straightforward: We
take two ratios and compare them. The first ratio is the sum of work
that has been resolved against the sum of work that is still remaining.
The second ratio is the sum of real time that's over again the sum of
real time that's upcoming.

projection= work_time_DONE/work_time_REMAIN - real_time_DONE /
real_time_REMAIN

You are behind if this value is negative and vice versa.

The expected work hours is your total work times the real time progress,
e.g. when 20 of 40hrs are over, half of your work is expected to be done
(5 of 10pts).

The work hours behind/ahead is difference of expected work hours done
and actual work time done, e.g. 20 of 40hrs real time are over, but only
1 out of 10 story points have been achieved. As the real time ratio is
0.5 we expect 10*0.5=5 story points to be done. As only 1 point is done,
you are behind by 4 points.


--
Cheers, Johannes
Agile Planning Team

0 votes


Permanent link
lbehzadi wrote:
Johannes thank you for this explanation, we are currently not using
story points, they are set to 0 in our tasks. How does that affect
expected work hours and ahead/behind number of hours?


That depends on your setting. For team and project release plan we
calculate progress based on a complexity attribute. By default, this is
story points and, hence, your bars don't make a statement. Iteration
plans always use hours for progress computation. The progress
computation is actually independent of the unit of work (story points,
hours, ...); it works the same for all of them.

--
Cheers, Johannes
Agile Planning Team

0 votes


Permanent link

What we do to calculate the projection is pretty straightforward: We
take two ratios and compare them. The first ratio is the sum of work
that has been resolved against the sum of work that is still remaining.
The second ratio is the sum of real time that's over again the sum of
real time that's upcoming.

projection= work_time_DONE/work_time_REMAIN - real_time_DONE /
real_time_REMAIN

The expected work hours is your total work times the real time progress,
e.g. when 20 of 40hrs are over, half of your work is expected to be done
(5 of 10pts).
The work hours behind/ahead is difference of expected work hours done
and actual work time done, e.g. 20 of 40hrs real time are over, but only
1 out of 10 story points have been achieved. As the real time ratio is
0.5 we expect 10*0.5=5 story points to be done. As only 1 point is done,
you are behind by 4 points.


Just came across this..
The text and the formula don't match.
I think the formula should be:
work_units_ahead= work_units_DONE - work_units_TOTAL * real_time_PASSED / real_time_TOTAL

Or am I just not getting the word 'projection'?

/Morten

0 votes


Permanent link
The progress is the difference between the Actual Hours and Expected hours.
Actual Hours      = (Sum time spent of all the work items)
Expected hours = (Sum estimates of all work items) * (Available hours from Start date of plan till now/ Available hours from Start date to End Date of the plan)
The available hours between 2 dates is calculated based on the allocation, work hours and absences of all the users part of the plan.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: May 27 '09, 7:43 a.m.

Question was seen: 6,370 times

Last updated: Oct 16 '12, 1:23 a.m.

Confirmation Cancel Confirm