Link Test Cases from one PA to a Test Plan from a different PA


Liora Milbaum (513275105) | asked Oct 13 '14, 2:29 a.m.
 CLM 4.0.4

Is it possible?

Thanks

Accepted answer


permanent link
Lily Wang (4.9k714) | answered Oct 13 '14, 3:15 a.m.
  Hi Liora,
This is not possible in RQM. You can see the discussion in https://jazz.net/forum/questions/118259/could-rqm-test-plan-connect-to-test-case-in-another-project-area for the explanation and workaround.
Hope it's helpful.