Copying test suites between project areas


Hivzo C. (1769) | asked Feb 14 '14, 7:52 a.m.

Hi.

I would like to know whether it is possible to copy test suites with or without corresponding test cases from one PA to another.

I am using CLM with RQM ver4.0.3.

Accepted answer


permanent link
Ara Masrof (3.2k15) | answered Feb 14 '14, 9:32 a.m.
JAZZ DEVELOPER
Hivzo,
See the online help topic :
Copying test artifacts
You can copy a test artifact from the list view or from the artifact editor. In general, the copy operation is referred to as duplicating test artifacts. Test artifacts can be duplicated to the same project area or to a different project area.

http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m3/index.jsp?re=1&topic=/com.ibm.rational.test.qm.doc/topics/c_copy_overview.html&scope=null


Hivzo C. selected this answer as the correct answer