Rolling up previous Start/End dates from a MS Project Plan Import into RTC

Can Start and End Date attributes be set from an imported MS Project Plan into RTC?  The planning feature allows the import and the dates to be preserved and rolled up, but the rolled up dates are NOT reflected in the Plan.  Once the Planned snapshot is taken, the Planned Start date begins on the Creation date of the work item, not the start date in the original MS Project plan.  

0 votes



One answer

Permanent link
Rob,

as far as I know you can import the data. However, the start and end dates are actually calculated by the scheduler and reflect what can be done with the allocation and associated users. In that respect RTC is a live plan that changes as time goes by.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Jul 22 '14, 1:55 p.m.

Question was seen: 3,611 times

Last updated: Jul 25 '14, 10:35 a.m.

Confirmation Cancel Confirm