why do my verified defects not show in the burnup totals?

I have burnup charts for my current sprint which show only defects. Defects which are in state resolved appear to show in this total for each day, but when they are then moved to verified, the spent-time figure is subtracted from the chart.
Both resolved and verified states are defined with the same stage group in the defect workflow so what else is the chart using to decide which items are included in the sum? Why would it ignore some states when making the burnup sum? I see the same problem with burndown. charts.
I am using the SCRUM template.

0 votes



One answer

Permanent link
 Did you modify the scrum workflow? By default, Verified is a different state group. [I won't argue whether or not that makes sense.] If the report is keying off of items in the Closed State Group, moving items to Verified would explain why they disappear from the burnup.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 21 '14, 10:37 a.m.

Question was seen: 3,204 times

Last updated: Jul 25 '14, 11:25 a.m.

Confirmation Cancel Confirm