Incorrect Time Remaining calculation?

One of my stakeholders reported a problem to me, that when adjusting the estimate (in his case from 6 w to 8 w), the time remaining is changed incorrectly.

For example, I have a task and I say Estimate is 3w .. time remaining changes to 3w.  I change estimate to 6w, it changes time remaining to 6w (okay, this works how I would imagine).  I save this.

Then I have gone in and in the Correction field, I put 8 w.  My time remaining changes to 2w 1d.  How is that possible?   Can someone explain how the Time Remaining field is calculated within a given work item (like Task) based on the Estimate and Correction values entered? 

Does it take into account what is already in the Time Remaining field?    For example, estimate 6w, then correction to 7w (updates time remaining to 7w).  If I then change correction to 8w, does it say that 8w (correction) minus 6w (estimate) = 2w longer.  Since the Time Remaining field previously said 7w, then I add 7w to the additional time to make 9w?



0 votes



One answer

Permanent link
hi Susan,

its being taken care by two work items:
Time Remaining is not updated when estimate is updated in eclipse client (304578)
and
Time remaining calculated incorrectly when updating estimates (322701)

you may want to add on your usecase to them to ensure its covered.

thanks,
Dinesh

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Jul 02 '14, 8:43 a.m.

Question was seen: 4,421 times

Last updated: Jul 02 '14, 8:49 a.m.

Confirmation Cancel Confirm