Is there any side effect of removing Constraint Type and Constraint Date from a work item?
![](http://jazz.net/_images/myphoto/bc9e13702af126db36d441ba5dd6c328.jpg)
In my RTC configuration, I have a WI type defined as "Task" from which I was requested to remove both "Constraint Type" and "Constraint Date" from the WI configuration.
In addition, this "Task" WI type is used to build Work Breakdown Structure, as child (and also as "Execution Item") of a parent WI type categorized as "Plan Item".
My concerns here are the following:
Is there any side effect of keeping those attributes out of the Task?
Is there any consequence of this in regards of planning?
Thanks in advance!
Vicky
In addition, this "Task" WI type is used to build Work Breakdown Structure, as child (and also as "Execution Item") of a parent WI type categorized as "Plan Item".
My concerns here are the following:
Is there any side effect of keeping those attributes out of the Task?
Is there any consequence of this in regards of planning?
Thanks in advance!
Vicky
Accepted answer
![](http://jazz.net/_images/myphoto/bc9e13702af126db36d441ba5dd6c328.jpg)
Hi Vicky,
Without the constaint type and constaint data, you will lose the schedule constaint for the Task work items which has the impact on the schedule calculation of a plan. Please see the explanation from https://jazz.net/library/article/663#ScheduleConstraints
In addition, the critical path is also calculated using constraints and other attributes.
Is there any special reason you want to remove the "Constraint Type" and "Constraint Date" from Task? You can think about to hide the attribute with a default value (such as "As Soon As Possible") assigned for the task work items.