RQM Test Plan PDF time display
1-) I created a test plan.
2-) I have entered 120 person hours to execution effort field and saved the test plan 3-) I have exported the test plan as PDF. In PDF execution effort is displayed as 5 days. How can i set it to 120 hours? |
Accepted answer
hi Serdar,
there is no way to customize the time display format in PDF printing Serdar Fener selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.