1-) I created a test plan.
2-) I have entered 120 person hours to execution effort field and saved the test plan
3-) I have exported the test plan as PDF.

In PDF execution effort is displayed as 5 days. How can i set it to 120 hours?

Accepted answer


permanent link
Chong Yuan Yin (7612) | answered Apr 10 '14, 2:42 a.m.
JAZZ DEVELOPER
hi Serdar,

there is no way to customize the time display format in PDF printing
Serdar Fener selected this answer as the correct answer