(18●6●6)
Apr 09 '14, 10:43 a.m.
1-) I created a test plan.
2-) I have entered 120 person hours to execution effort field and saved the test plan
3-) I have exported the test plan as PDF.
In PDF execution effort is displayed as 5 days. How can i set it to 120 hours?