 I am trying to add a related test plan to multiple tasks, stories, epics, etc. I have built a query to find all 300+ records that need this related test plan. Is there a way to to add the related test  plan to all of them at the same time?

Thanks,

-Justin

0 votes


Accepted answer

Permanent link
Hi Justin,
If all these work items appeared on a same RTC Plan, you could add a 'Related Test Plan' link to all of them in 1 go as per picture below ... so this might be a (partial) workaround for you
I tried a similar 'bulk-update' by using the 'Edit Multiple Work Items' option on a Query, but the 'Related Test Plan' link is not available as an Attribute change there.

Justin Hinman selected this answer as the correct answer

2 votes

Comments

Hi Christophe

   That will actually work perfectly! I ran into the same issue with 'Edit Multiple Work Items'. I didn't even think about looking at the plan.

  Thanks for your help!

-Justin

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Apr 08 '14, 6:27 p.m.

Question was seen: 3,288 times

Last updated: Apr 09 '14, 1:18 p.m.

Confirmation Cancel Confirm