Assigning Planned Execution Start and Completion Dates
Within RQM, is there a way to assign a planned execution start and end date for a Test Suite Execution Record? I would want to use this information to create a hill climber graph to show progress of testing.
|
2 answers
The test suite result would contain the actual start/end dates/times but the test suite execution record only contains the planned completion date/time.
Comments
Dana Watts
commented Apr 16 '14, 4:09 p.m.
Hi Paul,
See the 'Planned Execution Completed Date' field in the 'Summary' section.
Dana Watts
commented Apr 29 '14, 8:55 p.m.
Is this an attribute that we need to manually add? It's definitely not in the test suite or the test suite execution record.
Hi Dana,
Dana Watts
commented Apr 30 '14, 11:32 a.m.
I believe we have 4.0.0.1 and we're upgrading to 4.03 within the next few weeks.
Looks like this field was added in RQM 5.0.
showing 5 of 6
show 1 more comments
|
We've been able to work around this by creating a custom attribute to the TSER which will allow us to add a planned start and end date.
|