Assigning Planned Execution Start and Completion Dates
2 answers
The test suite result would contain the actual start/end dates/times but the test suite execution record only contains the planned completion date/time.
Comments
Hi Paul,
Thanks for the response. Unfortunately, I'm not able to find where to input the planned completion date/time on a test suite execution record. Would you be able to direct me on where to find this?
See the 'Planned Execution Completed Date' field in the 'Summary' section.
Is this an attribute that we need to manually add? It's definitely not in the test suite or the test suite execution record.
Unfortunately I don't have access to show a screenshot to show what we have available.
Hi Dana,
You may be using an older version of RQM. What RQM version are you using?
I believe we have 4.0.0.1 and we're upgrading to 4.03 within the next few weeks.
Looks like this field was added in RQM 5.0.
showing 5 of 6
show 1 more comments