To copy a test artifact in rqm to a differnt project area is very easy if the project area is located on the same jazz server. How it is possible to copy rqm artifacts to a different project area (this project are is located on the different jazz server)

0 votes



2 answers

Permanent link
Hello Martin,

maybe these helps:

a) Copying project settings to a new project
http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m5/topic/com.ibm.rational.test.qm.doc/topics/t_copyproject.html
b) RQM Copy Utility
https://jazz.net/wiki/bin/view/Main/RQMCopyUtility
-> Download: https://jazz.net/downloads/rational-quality-manager/releases/4.0.5?p=allDownloads

Regards,
Thomas

0 votes


Permanent link
Hi Martin,

in addition to the RQM Copy Utility mentioned by Thomas, you could refer to Dennis's answer here .
It points to a GUI-based "duplicate" capability.

Regards,
Stéphane

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,122

Question asked: Feb 03 '14, 9:52 a.m.

Question was seen: 5,106 times

Last updated: Feb 04 '14, 4:35 a.m.

Confirmation Cancel Confirm