RQM 4.x "Last Result Completed" column shows in-correct date for TCER's in progress / paused..
If the TER execution is not complete yet, the Last Result Completed field shows in-correct date value eg : 1 Jan 1970!
For eg. Please refer to the snapshot below The completed TER receives the current date as soon as it is saved after execution. But a TER in progress will not have a last result completed date. Is there a way to set the "Last Result Completed" to null or current date? Best Regards, Sunil |
Accepted answer
Hi Sunil,
Have created a defect RQM 4.x "Last Result Completed" column shows in-correct date for TCER's in progress / paused. (96841). Thanks, Deepa Sunil Kumar R selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.