Updating TER with Test plan information after starting the execution
Hello,
I have created the TER for a test case and started the execution, Can I update the TER with Test plan information?
Using RQM version 5.0.2
|
Accepted answer
Sorry Rashmi, you can not change the associated test plan of the TCER once it is created.
Rashmi B selected this answer as the correct answer
|