It's all about the answers!

Ask a question

Testcases associated to a TestPlan are not getting reflected appropriately in RQM


Rajesh Avanthi (10815145173) | asked Oct 03 '13, 6:47 a.m.
edited Oct 04 '13, 5:19 a.m.
 

Hi

Below is an example:


I have 2 TestPlans created (TestPlan1 & TestPlan2) in RQM


              TestCase1 is associated to TestPlan1 


similarly TestCase2 is associated to testPlan2 

NOTE:  Each of these Testcases have associated TCER already generated from within the TestPlan itself.


Now, if I open the "Execution Status using TCER Count" report



If i select TestPlanNew2, only the Testcases associated to it should be reflected in the TestCase section (Correct me if I'm wrong here), rather all the testCases are reflected .

Any inputs on this please ...


Thanks

One answer



permanent link
Vidya Malkarnekar (1.0k15) | answered Oct 04 '13, 9:43 a.m.
JAZZ DEVELOPER
Rajesh,

It is correct that "test cases" parameter shows all test cases across all test plans.  The "test case" parameter doesn't change depending on test plan chosen. It's best you don't choose any test cases at all, just select Test plan  and it will give you the correct results.  The  final report result in my case shows only test cases tied to the selected test plan.