Agile Scrum- abscences in RTC
Hi,
I femiliare with the User profile where I can report abscence. I am thinking of creating a task instead. For example: Half a day course: Creating a task and relate it to Absences category. I am doing it because of the following reasons: 1.The rezolution of scheduled abscences is in days and not houres. 2. I find it more easy to manage abscene of user that is working in several projects. My question: Do you recomend it otherwise? Do you find it problematic? I guess this will effect the reports in some how.. Thanks, Shirit.
|
One answer
Dinesh Kumar B (4.1k●4●13)
| answered Jul 30 '13, 6:20 a.m.
JAZZ DEVELOPER edited Jul 30 '13, 6:24 a.m.
using a Task would NOT help the Progress calculations in the various planning views.
There is an enhancement request for supporting finer resolution for absences is already logged : Support Scheduled Absences in increments less than a full day (78746) Adding your comments there would help... |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.